With the Grid Users Coalition warning that the Autumn Budget failed to adequately address the ongoing grid connection challenges facing businesses and developers, the issue of securing timely utility connections remains firmly in the spotlight. However, policy reform alone won’t fix delayed infrastructure. If developers want to protect their programmes and profitability, the industry must stop treating utility connections as a last-minute consideration and make it a critical priority on day one, argues Lee Ackerman – utilities general manager at Connectus Utilities.
While initiatives like the Great British Grid aim to untangle a UK connection queue that has grown to 700-750GW, waiting for Westminster or Ofgem to fix site-level delays is risky business. Even if regulatory reform moved overnight, projects would still stall for one simple reason – the construction industry continues to treat utility connections as a secondary consideration.
Across commercial and residential projects, we routinely see schemes tick every land, planning and funding box – only to hit a brick wall because power, water and fibre were left until the end of pre-construction. In a grid-constrained market, infrastructure cannot be an afterthought when it comes to project viability.
Hidden costs
When Connectus surveyed 100 construction and development professionals on multi-utility connections, the findings confirmed what site teams experience daily: avoidable delays are overwhelmingly driven by late engagement and fragmented procurement across multiple stakeholders.
When utilities are procured in silo, the consequences can be detrimental to the balance sheet. A delayed energisation date triggers a domino effect of stranded capital, extended finance and holding costs, along with postponed tenant handovers.
Furthermore, leaving connection applications until designs are complete often exposes local network constraints. Discovering mid-build that a scheme requires expensive off-site reinforcement or major civil redesigns can immediately wipe out margins.

However, taking a strategic, integrated view early unlocks significant commercial value. On recent mixed-use developments, reviewing connection routes and difficult works upfront – rather than defaulting to standard Distribution Network Operator (DNO) timelines – has saved more than 30% of initial connection quotes for one Connectus Utilities client.
As a result, this eliminated the costly inefficiency of redoing the same excavation works multiple times for separate connections.
Day-one discussion
To mitigate risk, utility strategy conversations belong in the feasibility room alongside the land acquisition and architectural plans, before a single spade hits the ground. This is even more important now that UK grid reforms are shifting the system from ‘first come, first served’ to ‘first ready, first connected’. Developers who fail to prepare land rights, planning and technical specifications early will find themselves pushed behind better-prepared schemes.
Early engagement allows project teams to map local network capacity, identify bottlenecks and assess alternative delivery routes – such as working with Independent Connection Providers (ICPs) and Independent DNOs – under a single, coordinated programme.
Building for tomorrow
Early planning must also look beyond immediate handover requirements. Securing just enough capacity to satisfy minimum compliance is a false economy.
The transition away from gas towards air source heat pumps, expanding EV charging mandates and on-site energy storage means modern developments demand significantly more electrical capacity than legacy benchmarks. We have to build capacity and resilience from day one. Schemes engineered purely for today’s baseline risk becoming stranded assets that require disruptive, high-cost retrofits within a few years of completion.
National infrastructure strategies and grid upgrades will eventually ease bottlenecks, but commercial developers do not have the luxury of waiting years for policy to filter down. Those who elevate utility infrastructure from a late-stage procurement exercise to a core pillar of early project design won’t just avoid delays – they will protect their margins and build assets fit for the future.
For more information or support with utility connections on your next project, visit: https://connectus-utilities.co.uk/